Eskom seeking corruption on disputed Karpowership emergency electricity tender

Green Connection is taking Karpowership to court over their awarding of an electricity tender.Image:Supplied

Green Connection is taking Karpowership to court over their awarding of an electricity tender.Image:Supplied

Published Apr 30, 2022

Share

Littered with controversy the proposed boost to the country’s woeful energy supply Eskom has required the winner of a tender which will add a further 2000 megawatts of electricity to the grid to indemnify it against any adverse outcomes from corruption allegations according to reports.

This comes after a losing bidder DNG Power Holdings took the process to court alleging that government officials were corrupt in awarding Turkish company Karpowership about 60% of the tender that will see it supplying energy from three ship-mounted power plants off the South African coast.

Reports also indicate that the company has refused to sign the indemnity clause and that Karpowership has yet to win environmental approval or have its ships in South Africa’s ports.

Green Connection has launched an application in the Gauteng High Court of Pretoria seeking to review and set aside the National Energy Regulator of South Africa’s (Nersa) decision to grant three electricity generation licenses to the Karpowership SA companies to operate powerships in the ports of Saldanha, Ngqura (Coega) and Richards Bay.

Green Connection is taking Karpowership to court over their awarding of an electricity tender.Image:Supplied

The organisation said that among other grounds of review included in the application, the Green Connection takes issue with Nersa having granted the generation licenses even though the Department of Forestry, Fisheries and the Environment (DFFE) had refused to grant environmental authorisations for the powerships, and without Nersa taking environmental considerations into account.

Green connection is also concerned over the negative climate change, environmental and economic impacts of the Karpowership companies being granted licenses to operate over a 20-year period to fill a short-term electricity supply gap.

Green Connection’s Community Outreach Coordinator Neville van Rooy said that The Green Connection believes that it does not make sense for Nersa to grant these electricity generation licenses to the Karpowership companies in these circumstances, and that in doing so Nersa has put the horse before the cart.

Van Rooyen said that since it was was first announced the whole Karpowership debacle has gone against the spirit of fairness, and we believe that the granting of the licenses is not in the interest of the people, electricity users or small-scale fishing communities whose livelihoods could be adversely affected by the negative environmental impacts of the Karpowerships.

Protester against the awarding of a controversial tender .Image:Supplied

“Furthermore, Nersa has granted these licenses on the back of public participation processes where critical information was redacted from the documents made publicly available, including the terms of any Power Purchase Agreement (PPA) with Eskom. It is because of these critical discrepancies and blatant lack of transparency that we have turned to the courts for justice for the people.” said van Rooyen.

The organisation has also filed a supplementary affidavit by energy expert Hilton Trollip in support of its application.

Trollip in his analysis critiqued of Nersa's rationale and explanations regarding its decision to grant licenses to the Karpowerships projects he said that understanding and trying to assess the economic implications of the Karpowership deals was challenging, since final official agreements and tariff information have been redacted and are not publicly available.

Green Connection says that to understand whether or not Karpowerships are a good economic investment, notwithstanding the environmental and potential subsequent social impacts, it is important to understand the country's energy systems and how this relates to the calculation of end-user costs.

The organisation said that in a nutshell, electricity generators’ costs are based on its technical and financial performance, thereby affecting the costs to users with Karpowerships seemingly coming in at the higher end of the cost spectrum.

“Karpowerships are supposed to be an emergency electricity generation solution, which means that they should dispatch electricity only when there is a shortage – incidentally, this is the only time it makes any economic sense – unless obliged by specific PPA conditions,”said Green Connection.

The Connection said they do not know what the PPA conditions are since this information has been redacted.

“So, are the human, environmental and economic costs of the Karpowerships justifiable since it is only cost-effective to use them in an emergency? On the other hand, if South Africa were to rely on Karpowerships more frequently, there will be a net economic loss because ultimately the electricity they generate will cost consumers more in the long run. The Green Connection believes that the Karpowerships are utterly unsuitable to meet the country’s dire short-term electricity generation needs,” said van Rooy.

The Connection is of the view that in granting these generation licenses, Nersa - as the custodian and enforcer of the electricity regulatory framework - is not safeguarding the needs and interests of present and future electricity users, as provided for in the Electricity Regulation Act (ERA).

The eco-justice organisation adds that it does not believe that Nersa is facilitating a fair balance between the interests of customers and end users, licensees, investors in the electricity supply industry and the public

The Green Connection said it does not understand why these electricity generation licenses were rushed through when environmental authorisations had been refused, when there is already so much controversy around this project, and while there are still so many questions about the suitability and sustainability of the 20-year Karpowership projects as measures to fill the short-term electricity generation gap.

The Green Connection have also queried why has long wondered why the government seems consistently willing to bend over backwards to progress these deals and hopes the court case will reveal its rationale.

“In the long-term, we believe that Karpowerships are an unsustainable and inefficient solution to our energy problems. The reality is that after the company has bled South Africa dry for twenty (20) years, these floating kettles will not even belong to the country, but instead will remain the property of the Karpowership companies and will leave at the end of the contract period. Additionally, at a time when we should be taking steps to address the climate change crisis, why is the Department of Mineral Resources and Environment (DMRE) so keen to lock South Africa into a 20-year project that will emit significant emissions of methane (a greenhouse gas with more climate warming potential than carbon dioxide)?” asked van Rooy.

What is also concerning the Connection is Parliament's decision to abandon a probe – launched less than a year ago – into allegations about Karpowerships as part of the Risk Mitigation IPP programme.

Green connection also said that other discrepancies and the deal has been tangled up in a raft of controversies,including having initially been granted an emergency environmental authorisation (which was later withdrawn after a public outcry).

“Subsequently, after undertaking an environmental impact assessment process, the Karpowership companies were refused environmental authorisations for all three projects. While the Karpowership companies have appealed against these refusals, the appeals have not yet been decided,” said Green Connection.